Project Description
Design included structural steel work (9,000 Ton), Crusher house, Transfer Towers (63 m high), Loco Shed, approx. 2,000 m long Conveyor galleries, Trestles, etc. The project was done in collaboration with Energo Engineering Projects. DCPL and Adani Power acted as approval agencies. The Project was completed within a tight deadline of 4 months, finishing design, obtaining approvals and delivering drawings. Economy in design enabled reduction in cost. Chinese Standard steel sections were used as required.